Client: Rio Tinto Iron Ore
Location: Mesa A (50km west of Pannawonica), Western Australia
Contract Duration: December 2023 – September 2024
Scope of Works:
Refurbishment of a dining facility originally constructed in 2008 and had minimal maintenance or repair works completed. The full scope of works included:
- Demolition of existing internals in dining and crib areas plus adjoining ablutions.
- Upgrade/renew of food servers and dining area.
- Renewal all dining area furniture, lighting and fit-out.
- Renew and upgrade existing bag drop area.
- Supply, installation and testing of all new mechaincal, electrical and hydraulic equipment.
- Undertake all works associated with the installation of temporary servery, including electrical and water feeds, and moving of equipment.
- Installation of all supplied crib and dining room equipment and appliances including assemble, set-up and install to manufacturer's instructions.
Key Project Achievements:
- Original scope plus additional unplanned scopes were all completed within tight schedule and to a high quality.
- Apprenticeship engagement.
David Hailes – Rio Tinto Iron Ore
“The entire team were a please to work with; their professionalism and proactive approach to all works was very good. There were several unplanned scopes, and their ownership of the project and resolution of any problem was exceptional.”